Karen Mauney-Brodek at RPD has shared this update on the Sussex Street steps:.
The Recreation and Park Department will proceed with rebuilding the steps at the entrance to Glen Canyon Park at the end of of Sussex Street. While RPD had expected to add this work to the contract for the other trails construction under way in Glen Canyon, the Sussex Street steps will now be a separate contract. RPD expects to bid and award the work by the end of July 2015. The work will not begin, however, until September 2015. This will avoid disruption of that entrance during the Silvertree Day Camp season. Construction is expected to take about six weeks, depending on weather or other unanticipated issues.