From Kelley McCoy, SFMTA spokeswoman:
I’ve received a schedule change from the contractors. Due to the rain forecasted for tomorrow, the construction schedule was revised and the crew will be focusing their efforts on the southeast/BART corner. Here is the revised schedule:
Monday
- Complete sidewalk and brickwork on the southeast (BART) corner
Sidewalk restoration on the southwest (Glen Park Market) and northeast (formerly Citibank) corners– will be finished in January
Tuesday
-
Pave southeast corner (if raining, work will be postponed to Wednesday)– Postponed to Wednesday due to rain forecast Lay brickwork on southwest corner along Bosworth– work will be finished in January- Demobilize barriers and clean-up at the intersection
Wednesday
- Pave southeast corner, clean up
Sidewalk restoration on northwest (Pebble’s Café) corner along Diamond– work will be finished in JanuaryFinish brickwork on southwest corner along Bosworth– work will be finished in January
The curb ramps at the southwest (Glen Park Market), northeast (formerly Citibank) and northwest (Pebble’s Café) corners will have temporary asphalt. In January, crews will return to finish the remainder of the work.