From Kelley McCoy, SFMTA:
Construction schedule for next three days (Sat 11/21, Sun 11/22, Mon 11/23)
· The 24-hour barricades on Bosworth are expected to be removed on Sunday. There will be closures during the week from 9am-4pm as needed for sidewalk work.
· Crews will work to complete the sidewalk reconstruction. This work will be on Saturday, Sunday and Monday. Work had been scheduled for Sunday in an effort to get the roadway open quickly.
· Paving open patched and clean-up of site on Monday 11/23 (if possible) and Tuesday, 11/24 (scheduled).
We are still expecting to finish the construction on Wednesday, 11/25. No work will be done during the holiday construction moratorium, between Thanksgiving Day and New Year’s Day.
Please let me know if there are any questions or concerns.
I will send another update before the Thanksgiving holiday.
Thanks,
Kelley McCoy