Construction Update #7 –August 23, 2017
Dear Neighbors,
We are rapidly approaching the end of our project and crews are preparing for roadway paving next week. Beginning Monday, August 28th 2017 our sub-contractor Esquivel Grading and Paving will start grinding and paving the roadway at the following locations along Diamond Heights Boulevard:
Phase 1 Paving (8/28/17-9/9/17)
*Portola Drive – Clipper St.
*Diamond St – Addison St
*Diamond St – Berkley Way
Phase 2 Paving (9/11/17-9/22/17)
*Clipper St. – Gold Mine Dr.
Phase 3 Paving (9/23/17-9/31/17)
*Gold Mine Dr. – Diamond St.
The remaining work on this project includes:
- Landscaping replacement along DHB at Carnelian Way
- Flashing Beacon pedestrian pole installation at the mid-way crossing at the shopping center
- Sidewalk installation and pedestrian guard-rail alongside Glen Canyon Park