DH Road Work – Update

Forwarded from SFPW:

Diamond Heights Boulevard Pavement Renovation and Water Replacement Project 
A PROJECT OF THE CITY’S TEN-YEAR CAPITAL PLAN

Construction Update #4 –March 7, 2017

 

Dear Neighbors,
Construction is underway. Although the rains last month caused several delays, we have completed the first block of water-main work between Duncan St. and Carnelian Way and curb-ramps at Arbor St. Curb-ramp work will continue along Diamond Heights Blvd for the next 6-8 months at various locations.

Work Activity for – March 2017
Addison and Gold Mine: curb-ramps installation

DHB Addison and Gold Mine to Berkeley Way (S): Water-main installation

Berkeley Way (south@ Canyon park): Adding sidewalk, ADA curb ramps, crosswalks and guardrails replacement at the trail entrance to Canyon Park

The contractor will generally work one block at a time to minimize any disruptions to area residents. Since we have several locations under this contract, it may be weeks or months before we start construction on your block. You will be notified approximately 2-weeks ahead of time with specific dates.

Traffic Impacts
Please observe the “no-parking” signs. Access to driveways will be provided at all times. Delays may occur while crews create a path for vehicles. Please allow extra travel time during construction

PROJECT DURATION: (12-months)
(Jan/winter 2017 – January 2018)
WORK HOURS: Mon-Fri 7:00 am – 3:00 pm
Sat-Sun 7:00 am – 3:00 pm

Overall Project Description
The project is located along Diamond Heights Boulevard between Portola and Sussex (12-blocks approx 2.2 miles) and consists of pavement renovation, curb construction, sidewalk replacement, sewer and water improvements. This work will be performed in the several phases. See sample sequence below:

1. Sidewalk installation and new ADA curb ramps
2. Water-line replacement (Water Dept)
3. Guard-rail replacement and installation
4. Sewer-line replacement
5. Roadway paving

For Project Updates
Email: dadisi.najib@sfdpw.org
Public Works: Ms. Dadisi Najib
Phone: 415-558-5281

After Hours Emergency:
Hoseley Corporation
925-788-2334 or 311

Advertisements

Leave a comment

Filed under City road work, DH, Uncategorized

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s