From Kelley McCoy, SFMTA:

 

Construction schedule for next three days (Sat 11/21, Sun 11/22, Mon 11/23)
·         The 24-hour barricades on Bosworth are expected to be removed on Sunday.  There will be closures during the week from 9am-4pm as needed for sidewalk work.
·         Crews will work to complete the sidewalk reconstruction. This work will be on Saturday, Sunday and Monday.  Work had been scheduled for Sunday in an effort to get the roadway open quickly.
·         Paving open patched and clean-up of site on Monday 11/23 (if possible) and Tuesday, 11/24 (scheduled).
We are still expecting to finish the construction on Wednesday, 11/25.  No work will be done during the holiday construction moratorium, between Thanksgiving Day and New Year’s Day.
Please let me know if there are any questions or concerns.
I will send another update before the Thanksgiving holiday.
Thanks,
Kelley McCoy
Public Relations Officer
San Francisco Municipal Transportation Agency
1 South Van Ness Avenue, 3rd Floor
San Francisco, CA 94103
Advertisements

Leave a comment

Filed under Uncategorized

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s